| This is an outline
of significant physical and electrical events that occurred
in a narrow window of time,before and during the cascade that
led to the blackout of August 14, 2003. This outline reviews
events beginning at approximately noon on that day, to provide
a "picture" of the sequence of events and how the
grid situation evolved over the afternoon. It focuses chiefly
on events that occurred on major transmission facilities (230
kilovolts and greater) and at large power plants.
This outline does not attempt to present or explain the
linkages between the sequences of events that are described.
Determining those linkages will require additional intensive
analysis over the weeks to come. In the coming weeks, our
experts will continue to analyze data from:
· the thousands of transmission line events that occurred
on the 138 kV system and on lower voltage lines over the several
hours before and during the grid's collapse
· the hundreds of events related to power plant interactions
with the grid during this period
· the conditions and operations on the grid before noon. Many
things happened well before noon — including reactive power
and voltage problems and flow patterns across several states
— that may be relevant in a causal sense to the blackout.
· any actions taken, or not taken, by system operators prior
to or during the outage.
The U.S./Canada Power Outage Task Force investigation is looking
at all of the above factors and more in order to refine these
data and dig deeper into what happened and why. This timeline
is not intended to indicate and should not be assumed to explain
why the blackout
happened, only to provide an early picture of what happened.
It is not intended to indicate and should not be assumed to
assign fault or culpability for the blackout. Determining
the specific causes of these failures requires a thorough
and professional investigation, which the bi-national investigative
team has undertaken. The above concerns and explanations will
be addressed in future reports prepared by the investigative
team and issued by the Joint U.S./Canada Task Force.
Note: The information in this report is
based on what is known about the August 14, 2003 blackout
as of September 11, 2003, and is subject to change based on
further investigation of this event.
August 14, 2003 Outage
Sequence of Events
This report provides the sequence of some
of the significant events that led to the blackout of the
electric systems in the Mid-west and Northeast United States
and eastern Canada on August 14, 2003. This explanation is
intended to provide a general understanding of how the blackout
evolved; it does not include every detail that is relevant
and necessary to fully understand the root causes of the blackout.
Such details are within the thousands of records of data that
need further analysis. Those data records include circuit
breaker operations, power plant startups and shutdowns, voltage
changes, power flow shifts, and load shedding. A joint team
from the United States and Canada is conducting a thorough
investigation of the blackout and will provide appropriate
details in a future report.
Event Times
The times listed in this summary were derived from the “time
stamp” that accompanied each data record. Whenever a circuit
breaker opens to disconnect a transmission line or closes
to reconnect a line, or generating unit is brought on line
or off, or voltage exceeds a specified limit, the time that
event occurred is recorded to the nearest second (and sometimes
to the fraction of a second).
In some cases, the investigators discovered that these time
stamps were not accurate because the computers that recorded
the information became backlogged, or the clocks from which
the time stamps were derived had not been calibrated to the
national time standard. Investigators must determine which
events are accurately time-stamped, and build from those events
to cross-check other system events from multiple sources to
verify the precise time for each event. Some of these events
are still not known to the exact second.
All times in the chronology are in Eastern
Daylight Time.
Voltage Collapse
One of the characteristics of the August 14 blackout was
an apparent “voltage collapse” that occurred on portions of
the transmission system surrounding and within the northern
Ohio and eastern Michigan load centers. Transmission system
voltage is needed to transfer electric power from the generation
stations to the load centers, and is somewhat similar in function
to water main pressure. Reactive power is the component of
total power that assists in maintaining proper voltages across
the power system. Sufficient voltage is maintained by supplying
the transmission system with reactive power from generating
stations and static devices called capacitors. Lightly-loaded
transmission lines also provide reactive power and help sustain
system voltage. Conversely, customer loads such as motors
and other electromagnetic devices consume reactive power,
as do heavily loaded transmission lines. Therefore, as transmission
lines become more heavily loaded, they consume more of the
reactive power needed to maintain proper transmission voltage.
Reactive power cannot travel long distances because it meets
considerable resistance over the transmission lines. Therefore,
reactive power sources need to be close to the point of reactive
power demand — for example, near the load centers. When heavily
loaded transmission lines disconnect, the lines that remain
in service automatically pick up portions of flow from the
disconnected line, which increases the reactive power consumed
by these lines. When reactive supply is limited, the increased
loading will cause a voltage drop along the line. If reactive
supply is not provided at the end of the line, the voltage
could fall precipitously. At that point, the transmission
system can no longer transfer electric power from distant
generation to energy users in load centers.
In some instances, the reactive power demand
within an area is too great for the local generating units
to supply. In those cases, the units can trip off line (automatic
separation or shut-down), either from reactive power overload,
or because the system voltage has become too low to provide
power to the generators’ own auxiliary equipment, such as
fans, coal pulverizers, and pumps.
The power system is designed to ensure that if conditions
on the grid (excessive or inadequate voltage, apparent impedance
or frequency) threaten the safe operation of the transmission
lines or power plants, the threatened equipment automatically
separates from the network to protect itself from physical
damage. Physical damage, if allowed to occur, would make restoration
more difficult and much more expensive.
Pre-blackout Conditions
Most of the events that appear to have contributed to the
blackout occurred during the period from about noon EDT until
4:13 p.m. EDT. Generation and transmission operating events
plus scheduled interchange through the systems in the region
may have affected events later in the day. The investigators
are studying these events beginning at 8 a.m. on August 14
to determine whether they were significant to the blackout.
Map Key
The key on the right explains the lines and symbols on the
maps that accompany this description of events. An “open path”
or “open line” means that one or more transmission lines can
no longer carry electricity between two areas; a “generator
trip” means the generator separates from the grid and stops
producing electricity.
Events Leading to the Blackout
12:05:44 – 1:31:34 PM – Generator trips
1. 12:05:44 – Conesville Unit 5 (rating 375 MW)
2. 1:14:04 – Greenwood Unit 1 (rating 785 MW)
3. 1:31:34 – Eastlake Unit 5 (rating: 597 MW)
Conesville plant is in central Ohio and Greenwood
plant is north of the Detroit area. Greenwood Unit 1
tripped at 1:14:04 and returned to service at 1:57.
Eastlake Unit 5 is in northern Ohio along the southern shore
of Lake Erie and is connected to the 345 kV transmission
system. These generating unit trips (shutdowns) caused
the electric power flow pattern to change over the transmission
system.
|
 |
2:02 PM – Transmission line disconnects in
southwestern Ohio
4. Stuart – Atlanta 345 kV
This line is part of the transmission pathway from
southwestern Ohio into northern Ohio. It
disconnected from the system due to a brush fire
under a portion of the line. Hot gases from a fire can
ionize the air above a transmission line, causing the
air to conduct electricity and short-circuit the conductors.
3:05:41 – 3:41:33 PM – Transmission lines disconnect between
eastern Ohio and
northern Ohio
5. 3:05:41 – Harding-Chamberlain 345 kV
6. 3:32:03 – Hanna-Juniper 345 kV
7. 3:41:33 – Star-South Canton 345 kV |
 |
These three transmission lines are part
of the pathway into northern Ohio from eastern Ohio. At this
time, the reason for the Harding-Chamberlain line going out
of service is unknown. The Hanna-Juniper line contacted a
tree, creating a short-circuit to ground that caused the line
to disconnect itself. The Star-South Canton line had disconnected
and reclosed twice earlier in the day, but the significance
of those events is not yet clear.
With these lines disconnected, the effectiveness
of the transmission path from eastern Ohio into the northern
Ohio area was reduced. The electricity that had been flowing
over these lines instantly began flowing over other transmission
lines, including the underlying 138 kV systems, that connect
northern Ohio to the grid. However, this new power flow pattern
began to overload those other lines as well. As voltage was
dropping, demand of about 600 MW disconnected in the northern
Ohio area from industrial customers (whose motors dropped
off line due to low voltage) and distribution-level customers
who were disconnected automatically from the 138 and 69 kV
transmission system.
3:45:33 – 4:08:58 PM – Remaining transmission
lines disconnect from eastern into northern Ohio
8. 3:45:33 – Canton Central-Tidd 345 kV
9. 4:06:03 – Sammis-Star 345 kV
Canton Central-Tidd disconnected at 3:45:33 and
reconnected 58 seconds later. However, the Canton
Central 345/138 kV transformers disconnected and
did not reconnect, isolating the 138 kV system from
the 345 kV support at the Canton Central
substation. The Sammis-Star 345 kV line then
disconnected at 4:06:03, which completely blocked
the 345 kV path into northern Ohio from eastern
Ohio. This left only three paths for power to flow
into northern Ohio: 1) from northeastern Ohio and |
 |
Pennsylvania around the southern shore
of Lake Erie, 2) from southern Ohio (recall, however, that
part of that pathway was severed following the Stuart-Atlanta
line trip at 2:02), and 3) from eastern Michigan. This also
substantially weakened northeast Ohio as a source of power
to eastern Michigan, making the Detroit area more reliant
on the west-east Michigan lines and the same southern and
western Ohio transmission lines.
During the period 3:42:49-4:08:58, multiple
138 kV lines across northern Ohio disconnected themselves.
This blacked out Akron and the areas west and south.
4:08:58 – 4:10:27 PM – Transmission lines
into northwestern Ohio disconnect, and generation trips in
central Michigan
10. 4:08:58 – Galion-Ohio Central-Muskingum
345 kV
11. 4:09:06 – East Lima-Fostoria Central
345 kV
12. 4:09:23-4:10:27 – Kinder Morgan
(rating: 500 MW; loaded to 200 MW)
|
 |
When the Galion-Ohio Central-Muskingum
and East Lima-Fostoria Central transmission lines disconnected,
this blocked the transmission paths from southern and western
Ohio into northern Ohio and eastern Michigan. Thus the combined
northern Ohio and eastern Michigan load centers were connected
only by the transmission lines from: 1) northeastern Ohio
and Pennsylvania along the southern shore of Lake Erie; 2)
western Michigan via the west-east lines that cross the state;
and 3) Ontario. Eastern Michigan was connected to northern
Ohio only by three 345 kV transmission lines near the southwestern
bend of Lake Erie. The Kinder Morgan generating unit tripped
(shut down) in central Michigan (loaded to 200 MW).
Power flows became heavy from Indiana and
over the west-east Michigan transmission lines to serve loads
in eastern Michigan and northern Ohio. The reduced transmission
capacity serving the northern Ohio load centers resulted in
the transmission
voltage becoming depressed in that area as load exceeded the
rapidly declining power delivery capability.
At about 4:09, the Eastern Interconnection frequency rose
by 0.020 – 0.027 Hz, which represents a demand loss in the
range of 700 – 950 MW.
4:10:00 – 4:10:38 PM – Transmission lines disconnect across
Michigan and northern Ohio, generation trips off line in northern
Michigan and northern Ohio, and northern Ohio separates from Pennsylvania
13. 4:10 – Harding-Fox 345 kV
14. 4:10:04 – 4:10:45 – Twenty
generators along Lake Erie in
northern Ohio (loaded to 2174
MW total)
15. 4:10:37 – West-East Michigan
345 kV
16. 4:10:38 – Midland
Cogeneration Venture (loaded
to 1265 MW)
17. 4:10:38 – Transmission system
separates northwest of Detroit
18. 4:10:38 – Perry-Ashtabula-Erie
West 345 kV
|
 |
Twenty generators (loaded to 2174 MW) tripped
off line along Lake Erie during the period 4:10:04 – 4:10:45.
The loss of this generation increased the power flows into
the northern Ohio and eastern Michigan load centers on the
remaining paths, which included the west-east transmission
lines that cross Michigan.
The west-east Michigan 345 kV paths then disconnected at 4:10:37,
leaving eastern Michigan connected by only a circuitous path
around northern Michigan that disconnected one second later,
and the connections to Ontario and northern Ohio. Investigators
are still studying the power flows that resulted.
At 4:10:38, the Midland Cogeneration Venture
(MCV), loaded to 1265 MW, tripped off line.
The MCV generation trip imposed heavier
flows on the remaining transmission system, and left eastern
Michigan and northern Ohio with very depressed voltages. The
remaining transmission paths into the Detroit area from the
northwest separated.
At 4:10:38, the Perry-Ashtabula-Erie West 345 kV transmission
line tripped, severing the path into the northern Ohio area
from Pennsylvania along the southern shore of Lake Erie.
Summary of the Situation at 4:10:38 When the Perry-Ashtabula-Erie
West 345 kV transmission line disconnected at 4:10:38, the
entire eastern Michigan and northern Ohio load centers had
little generation left available to them and the voltage was
declining. The only connection between those load centers
and the rest of the Eastern Interconnection was at the interface
between the Michigan and Ontario systems. Also, the frequency
was declining in northern Ohio in those areas that had separated
from the Interconnection.
When the transmission lines along the southern
shore of Lake Erie disconnected, the power that had been flowing
along that path immediately reversed direction and began flowing
in a giant loop counterclockwise from Pennsylvania to New
York to Ontario and into Michigan.

We now turn our attention to the Pennsylvania,
New York, Ontario, Québec, and Maritimes areas.
4:10:40 – 4:10:44 PM – Four transmission
lines disconnect between Pennsylvania and New York
19. 4:10:40 – Homer City-Watercure Roa d
345 kV
20. 4:10:40 – Homer City-Stolle Road 345 kV
21. 4:10:41 – South Ripley-Dunkirk 230 kV
22. 4:10:44 – East Towanda-Hillside 230 kV

Responding to the surge of energy flowing
north out of Pennsylvania through New York and Ontario into
Michigan, these four lines disconnected within four seconds
of one another and separated Pennsylvania from New York.
At this point, the northern part of the
Eastern Interconnection (which still included the rapidly
dwindling load in eastern Michigan and northern Ohio) remained
connected to the rest of the Interconnection at only two locations:
1) in the east through the ties between New York and New Jersey,
and 2) in the west through the 230 kV transmission line between
Ontario, Manitoba, and Minnesota.
Heavy power flows were moving northward
over the New York-New Jersey ties.
4:10:41 PM – Transmission line disconnects
and generation trips in northern Ohio
23. Fostoria Central-Galion 345 kV
24. Perry 1 nuclear unit (rated 1252 MW)
25. Avon Lake 9 unit (rated 616 MW)
26. Beaver-Davis Besse 345 kV
The Fostoria Central-Galion line forms part
of the pathway from central to northern
Ohio. That path was already blocked by the
combination of the Galion-Muskingum-
Ohio Central line disconnecting at 4:08:58,
and the East Lima-Fostoria Central line
disconnecting at 4:09:06. |
 |
Perry 1 nuclear unit, located on the southern
shore of Lake Erie near the border with Pennsylvania, and
Avon Lake 9, located near Cleveland, tripped off line at virtually
the same time.
When the Beaver-Davis Besse 345 kV line,
which connects the Cleveland and Toledo areas, disconnected,
it left the Cleveland area isolated from the Eastern Interconnection.
Cleveland area load was disconnected first by automatic underfrequency
load shedding, and finally by the disconnection of the transmission
lines.
4:10:42 – 4:10:45 PM – Transmission paths
disconnect in northern Ontario and New Jersey, isolating the
northeast portion of the Eastern Interconnection
27. 4:10:42 – Campbell unit 3 (rated 820
MW) trips
28. 4:10:43 – Keith-Waterman 230 kV
29. 4:10:45 – Wawa-Marathon 230 kV
30. 4:10:45 – Branchburg-Ramapo 500 kV

At 4:10:43, eastern Michigan was still connected
to Ontario, but the Keith-Waterman 230 kV line that forms
part of that interface disconnected.
At 4:10:45, the Ontario system separated
when the Wawa-Marathon 230 kV line disconnected along the
northern shore of Lake Superior. The portion of Ontario to
the west of Wawa remained connected to Manitoba and Minnesota.
At the same time, the Branchburg-Ramapo
500 kV line was now the remaining link between the Eastern
Interconnection and the area ultimately affected by the blackout,
and that line disconnected at 4:10:45 along with the underlying
230 and 138 kV ties in New Jersey. This left the northern
part of New Jersey connected to New York. Pennsylvania and
the remainder of New Jersey remained connected to the Eastern
Interconnection.
At this point, the Eastern Interconnection
was split into two sections separated by an east-to-west line.
To the north of that line was New York City, northern New
Jersey, New York, New England, the Maritime
provinces, eastern Michigan, the majority
of Ontario, plus the Québec system. To the south of that line
was the rest of the Eastern Interconnection, which was not
affected by the blackout.
4:10:46 – 4:10:55 PM – New York splits east-to-west.
New England (except
southwestern Connecticut) and the Maritimes separate from
New York and remain intact.

During the next nine seconds, several separations
occurred between the areas in the northern section of the
Eastern Interconnection.
31. 4:10:46– 4:10:55 – New York-New England
transmission lines disconnect
The ties between New York and New England
disconnected during this period, and most of the New England
area became an island with generation and demand balanced
close enough that it could remain operational. However, southwestern
Connecticut was separated from New England and remained tied
to the New York system for about one minute.
32. 4:10:48 – New York transmission splits
east-west.
The transmission system in New York split
along an east-west line, with northern New Jersey and southwestern
Connecticut connected to the eastern part of the New York
system, and Ontario and eastern Michigan connected to the
western part. During the next second, Ontario and New York
would separate,
with 15% of the demand across New York
state disconnected automatically. About 2500 MW of Ontario
demand automatically disconnected as Ontario attempted to
rebalance its system.
4:10:50 – 4:11:57 PM – Ontario separates
from New York west of Niagara Falls and west of St. Lawrence.
Southwestern Connecticut separates from New York and blacks
out.
33. 4:10:50– The Ontario system just west
of Niagara Falls and west of St. Lawrence separates from New
York.
34. 4:11:22 – Long Mountain – Plum Tree 345
kV
35. 4:11:57 – Remaining transmissio n lines
between Ontario and eastern Michigan separate

The Ontario-New York separation at 4:10:50
left New York’s and Ontario’s large hydro and some thermal
generators at Niagara and St. Lawrence, as well as the 765
kV and direct current interties with Québec, connected to
the New York system, supporting the demand in upstate New
York just south of Lake Ontario. Three of the transmission
circuits near Niagara automatically reconnected Ontario to
New York at 4:10:56. Another 4500 MW of Ontario demand automatically
disconnected. At 4:11:10, the Niagara lines disconnected again,
and New York and Ontario again separated. Most of Ontario
blacked out after this separation, leaving 22,500 MW of demand
disconnected out of a total demand of about
24,000 MW. The eastern New York island blacked out with only
scattered small pockets of service remaining. The western
New York island continued to serve about 50% of the demand
in that island.
When Long Mountain-Plum Tree (connected to Pleasant Valley
substation in New York) disconnected, it left southwestern
Connecticut connected to New York only through the 138 kV
cable that crosses Long Island Sound. About 500 MW of southwest
Connecticut demand was disconnected by automatic grid operations.
Twenty-two seconds later the Long Island Sound cable disconnected,
islanding southwest Connecticut and blacking it out.
4:13 PM – Cascading sequence essentially
complete

The major portion of the northern section
of the Eastern Interconnection (the area within the dotted
line in the map above) was blacked out.
Some isolated areas of generation and load
remained on line for several minutes. Some of those areas
in which a close generation-demand balance could be maintained
remained operational; other generators ultimately tripped
off line and the areas they served were blacked out.
One relatively large island remained in
operation serving about 5700 MW of demand, mostly in western
New York. This service was maintained by generating stations
south of Lake Ontario with Ontario generators at Niagara and
St. Lawrence as well as the 765 kV and DC interties with Québec.
This island formed the basis for restoration in both New York
and Ontario.
Conclusion
This sequence of events for the August 14, 2003 blackout
summarizes some of the many signif icant events that occurred
before and during this widespread and complex system failure.
It reflects events that have been identified and verified
as of September 10, 2003. Much more data collection, analysis,
and research must be completed before the Joint United States-Canada
Power Outage Task Force will be able to state with confidence
exactly what happened and why it happened. Our understanding
of the events described here, and of those not yet fully catalogued,
may change as the investigation progresses. The Task Force’s
future reports will include a more detailed timeline, and
will address the causal relationships among these events.
|